VENDOR INVOLVEMENT AND CONCURRENT ENGINEERING: METHODS IN REDUCING DEVELOPMENT TIME FOR NEW MODEL IN AUTOMATIVE INDUSTRY

Authors

  • Nik Mohd. Zuki Nik Mohamed Universiti Putra Malaysia
  • Hasan Yudie Sastra Universiti Putra Malaysia
  • Mohd. Sapuan Salit Universiti Putra Malaysia
  • Napsiah Ismail Universiti Putra Malaysia
  • Prithivi Raj Arora Universiti Putra Malaysia
  • Abu Bakar Abdul Hamid Universiti Putra Malaysia

Abstract

ABSTRACT

A study of method improvement to reduce development time for new model in automotive industry is presented in this paper. The approach taken is by studying the existing practice in car development. It was found that in the current practice of car development, project planning and master schedule were not officially endorsed by all related departmental heads, which resulted in too ambitious and unrealistic schedules. Other problem includes lack of comprehensive market research to gauge the car implementation timing, styling and manufacturing trend in the process of project planning. It was also found that benchmarking exercise was carried out on already released product and for future product. The study suggested various ways for method improvement such as through effective benchmarking process, audit of vendor capability, excellent computer facility, official endorsement of project planning and master schedule by related departmental heads and comprehensive market research.

References

Abu Bakar, A.H. (2003), An Analysis on Policy Initiatives Involving Small and Medium Enterprises In Malaysia. Ph.D Thesis, Derbyshire Business School, University of Derby, United Kingdom.

Abu Bakar, A.H. and Rohaizat, B. (2002), Pengurusan Pembelian. McGraw Hill. Malaysia.

Altiok, T. (1997), Performance Analysis of Manufacturing System. New York: Springer-Verlag.

Burgess, T.F, Byrne. K and Kidd, C. (2003), Making Project Status Visible in Complex Aerospace Projects, International Journal of Project Management, vol. 21, pp. 251-259.

Efstathiades, A. (2002), Strategic Planning, Transfer and Implementation of Advanced Manufacturing Technologies (AMT): Development of an Integrated Process Plan, Technovation Journal, vol. 22, pp. 201-212.

Harrington, H.J. (1987), The Improvement Process, New York: McGraw Hill.

Institute for Advanced Engineering, (2001), Tailored Blank Technology at IAE. Seoul

Maddux, G.A. and Souder, W.E. (1993), Overcoming Barriers to the Implementation of Concurrent Engineering: in Concurrent Engineering, London: Chapman and Hall.

Ogawa, E. (1984), Modern Production Management: A Japanese Experience, Tokyo: Nordica Int. Ltd.

Sapuan, S.M. (1998), A Concurrent Engineering Design System for Polymeric-Based Composite Automotive Components, ph.D Thesis, De Montfort University, UK.

Downloads

Published

2017-04-06

How to Cite

Nik Mohamed, N. M. Z., Sastra, H. Y., Salit, M. S., Ismail, N., Arora, P. R., & Abdul Hamid, A. B. (2017). VENDOR INVOLVEMENT AND CONCURRENT ENGINEERING: METHODS IN REDUCING DEVELOPMENT TIME FOR NEW MODEL IN AUTOMATIVE INDUSTRY. Jurnal Kemanusiaan, 2(2). Retrieved from https://jurnalkemanusiaan.utm.my/index.php/kemanusiaan/article/view/134

Issue

Section

Articles